Wheat flour (packaged)58—Ginger (imported)167—Ginger (local)154—Aman rice (medium)56—Aman rice (coarse)48—Aman rice (fine)72—Iodised salt (packaged)32—Green chilli218—Broiler chicken162—Mutton900—Sugar (local)132—Chickpeas (whole)85—Farm eggs (red)47—Onion (local)60—Boro rice (medium)55—Boro rice (coarse)47—Boro rice (fine)66—Beef729—Mung dal122—Garlic (imported)192—Garlic (local)173—Soybean oil163—
Updated 20 November 2026
Dhaka22°Heavy rainHumidity 99%Wind 10 km/hRain 2.7 mm

Manu embankment: Tk 996 crore project stuck on land, local resistance and the border

About 60 percent of a Tk 996 crore project approved in 2020 to protect the Manu River’s risky embankments in Moulvibazar is done; land acquisition, local obstruction and Indian objections are holding up the rest.

Manu embankment: Tk 996 crore project stuck on land, local resistance and the border
Environment

A Tk 996.28 crore project to protect the Manu River’s risky embankments and banks, and with them the people of Moulvibazar from floods, was approved by ECNEC in 2020 and started in 2021. Due to finish in June 2023, it was extended to June 2026, yet about 40 percent of the work remains. Land acquisition problems, local obstruction and Indian objections are holding up several packages, Ajker Patrika reports.

The Bangladesh Water Development Board (BWDB) said the project, to repair about 30 km of risky embankment in Sadar, Rajnagar and Kulaura upazilas, was split into 70 packages with about 20 contractors. Work on 1,450 metres of embankment in no man’s land at Telibil, Bagjur and Nishchintapur on the Kulaura border has not begun. India says the boundary pillar lies in the middle of the Manu; with the Joint Rivers Commission not resolving the issue, blocks made three years ago for 650 metres of embankment at Telibil are still lying unused.

At the century-old Kaukapon bazar in Hajipur union, Kulaura, most of the eastern side of the market, about 40 shops and part of a road have fallen into the river, and work on the bazar’s 450 metres of embankment has not been possible. At Telibil the embankment on the Bangladesh side has broken and moved close to homes, and residents say water spills over when the river rises.

Telibil resident Jamal Hossain said people live in fear when the river rises and the embankment will break if it is not repaired. Junaid Ahmed of Kaukapon said thousands of lives are left uncertain every monsoon because a few people have stopped the work. Contractors’ representatives said they are losing money after keeping blocks ready for three years without being able to use them.

Moulvibazar BWDB executive engineer Khaled Bin Olid said about 60 percent of the project is done, the rest cannot go ahead because of local objections, and there is no progress on the no man’s land work. He said local people beat one of the BWDB’s staff at a work site in Rajnagar. The report is by Ajker Patrika’s Moulvibazar correspondent Mahidul Islam.